Job completed for Commercial Building Sewage Backup in Cross River, NY

Completion date: November 3, 2022

Location: Cross River, NY

Why did the customer contact us?

The Property Manager for this office building met with Rob our Project Manager after their septic system backed up causing wastewater to spread throughout their offices. They were concerned about the foul odors, water damage and mold growth. The management company advised they wanted us to send a cleanup crew asap!

Solutions provided:

Our IICRC Certified Project Manager Rob, assessed the damage, measured the areas, and went over the scope of work with the Property Manager.

The First Response crew were then dispatched to begin prepping the work area, extracting the sewage water, and disinfecting all affected areas. The crew set up multiple air scrubbers, 5 air movers and 3 humidifiers to dry out the offices.

Photos & Videos:

Office Lobby
Large View Icon
Office Lobby
Reception Desk
Large View Icon
Reception Desk
Extractor at work
Large View Icon
Extractor at work
Moisture reading
Large View Icon
Moisture reading